On the D7 section Kutrovice – Panenský Týnec, we are constructing a bridge that spans the Bílichovský Creek valley and Road III/23733. The seven-span prestressed concrete structure is being built using a movable formwork traveler, which enables fast, precise, and safe construction in individual segments.
The bridge superstructure was concreted in a total of seven stages, with the interval between individual pours reduced to as little as 17 days. In total, approximately 2,100 m³ of concrete has been used.
The project is scheduled for completion in June 2026.
| Construction period | 2025 - 2026 |
| Contractor | COLAS CZ, a.s. |