Bridge over the Bílichovský Creek Valley as part of the new D7 motorway

On the D7 section Kutrovice – Panenský Týnec, we are constructing a bridge that spans the Bílichovský Creek valley and Road III/23733. The seven-span prestressed concrete structure is being built using a movable formwork traveler, which enables fast, precise, and safe construction in individual segments.

The bridge superstructure was concreted in a total of seven stages, with the interval between individual pours reduced to as little as 17 days. In total, approximately 2,100 m³ of concrete has been used.

The project is scheduled for completion in June 2026.

 

 

Construction period2025 - 2026
  
ContractorCOLAS CZ, a.s.
 